Calik Enerji Swiss AG

1336 MW Kozienice Combined Cycle Power Plant - SERV Covered Financing

Borrower(s)
Calik Enerji Swiss AG
Industry
Power/Gas-fired combined cycle
Area of finance
Project & Infrastructure Finance
Region
Europe
Europe
Countries
Poland

Deal Overview

$315.9 million SERV-backed facility supporting the advance payment bond for the turnkey construction of the 1.336 GW hydrogen-ready Kozienice Combined-Cycle Power Plant in Poland.

Deal Volume
$315.91m
Financial Close
24/10/2025
Dealmakers
Sources
Submitted by participant(s),

Did you work on this deal ?

This deal page needs more information from those involved.

Tag yourself TAG A COLLEAGUE SUGGEST AN EDIT

Tranches

To view all tranche and pricing information, login or upgrade to a subscription here

Project Deals

1336 MW Kozienice Combined Cycle Power Plant
$316m
Greenfield
Gas-fired combined cycle
Europe
Europe
Poland